Insights from Willow Private Finance

Clear answers for complex finance decisions.

Willow Private Finance is an independent, whole-of-market finance brokerage. We help individuals, families, businesses and professional advisers navigate mortgages, specialist property finance, private banking, portfolio-backed lending and protection, particularly when standard routes do not fit.

Property finance Private clients Business & protection Market intelligence
FCA regulated Independent advice Established in 2008 UK & international clients
Explore Willow's guides and expertise
Building Safety Levy: Recheck Development Finance Now
Market Intelligence

A New Development Cost Can Change More Than the Profit Margin

The Building Safety Levy comes into operation on 1 October 2026. For affected developments, the immediate finance question is whether the existing appraisal, senior facility and equity commitment still work once the additional cost is included.

Development Finance / Development Viability

The Building Safety Levy Starts on 1 October — Does Your Development Finance Appraisal Still Work?

Nine in ten SME developers surveyed believe the new levy will make some schemes unviable. For borrowers and lenders, the immediate issue is whether developments appraised before the final levy position was known still support the same debt, equity and profit assumptions.

A development that worked on paper six or twelve months ago may produce a materially different funding requirement once the Building Safety Levy is incorporated. With the levy taking effect from 1 October, developers with affected schemes have a defined window in which to retest their capital stack.

Property developers are accustomed to managing moving costs. Build prices change, interest accrues for longer than expected, Section 106 obligations evolve and sales values can move between site acquisition and completion.

The Building Safety Levy adds another variable — but one that is now sufficiently defined to be incorporated into development appraisals.

From 1 October 2026, the levy comes into operation in England and applies to qualifying building control applications and notices submitted from that date, subject to the exemptions and charging conditions set out in the regulations.

That commencement date is becoming increasingly significant for developers because the latest SME sentiment data suggests the industry's concern is not merely theoretical.

The Development Finance Issue

The important question is not simply “How much will the levy cost?” It is whether adding that liability changes peak debt, lender leverage, required equity and the developer's return sufficiently to alter the finance structure.

Nine in Ten SME Developers Are Concerned About Viability

The latest SME developer sentiment survey from the Home Builders Federation and Quantum Development Finance, based on responses from 114 SME housebuilders, found that 90% believe the Building Safety Levy will make some developments unviable.

More significantly, the survey indicates that the consequences are already affecting behaviour. Some 36% of respondents said they had delayed, redesigned or cancelled schemes because of the levy, while 69% said it made them less likely to invest in future developments.

This is occurring in a market where viability is already the dominant supply-side constraint. According to the survey, 75% of developers identified development viability as a barrier to housing delivery.

90% believe the levy will make some developments unviable
36% have already delayed, redesigned or cancelled schemes
69% say the levy makes future investment less likely

Those figures matter for development lenders because finance is ultimately advanced against an appraisal. If the economics supporting that appraisal deteriorate, the amount and structure of debt that can prudently sit behind the scheme can change with them.

How the Building Safety Levy Works

The government's Building Safety Levy is designed to contribute towards the cost of addressing historic building safety defects. It applies in England and will be administered through the building control process.

Government guidance confirms that the levy becomes operational on 1 October 2026. Qualifying applications for building control approval relating to new dwellings, purpose-built student accommodation and certain residential conversions submitted on or after that date can fall within the regime.

The charge is principally calculated using the amount of chargeable residential floorspace and the applicable rate per square metre for the local authority in which the building is situated.

Rates vary geographically because they have been weighted using local house prices. This means the levy cost on an otherwise similar scheme can differ materially according to location.

Developments meeting the regulatory definition of a previously developed site receive a rate that is half the standard rate for the relevant local authority.

Government guidance states that, broadly, at least 75% of the land within the relevant planning-permission redline must satisfy the regulatory definition of previously developed land for the discounted rate to apply.

Brownfield Does Not Simply Mean “Previously Used”

Developers should establish whether the site meets the specific regulatory definition of previously developed land. The 50% discounted levy rate depends on the scheme satisfying that definition rather than simply being described commercially as a brownfield development.

Why Apartment Schemes Can Be Particularly Sensitive

The effect is not necessarily uniform across different types of residential development.

Government guidance confirms that chargeable floorspace can include qualifying communal areas as well as the floorspace within individual dwellings or PBSA accommodation.

That makes the detailed calculation particularly relevant to apartment and student-accommodation schemes, where corridors, entrance areas and other communal residential space can form a meaningful part of total gross internal area.

HBF estimates that the levy adds around £2,320 to the cost of a typical new home, but an average figure should not be substituted for a scheme-specific calculation.

A London apartment development with substantial communal floorspace can face a very different levy liability from a lower-density housing scheme on previously developed land elsewhere in England.

That difference matters directly to the development appraisal.

Why This Is a Development Finance Issue

Consider a scheme originally acquired and financed in 2024 or 2025.

The original appraisal may have incorporated land acquisition, construction, professional fees, contingency, CIL, Section 106 obligations, finance costs and expected sales values. The lender may then have sized its facility against total cost and GDV while the developer committed the required equity.

If a further material development cost is subsequently added, the effect does not stop at a reduction in developer profit.

The additional expenditure may increase total development cost and the amount of cash required at peak utilisation. Depending on the lender's facility and leverage parameters, the additional cost may be funded by debt, by the developer or by a combination of both.

In a scheme already operating relatively close to the lender's maximum loan-to-cost or loan-to-GDV limits, there may be little additional senior debt capacity available.

The developer may therefore have to contribute additional equity or consider a different capital structure.

The Appraisal Needs to Be Re-Run, Not Simply Adjusted at the Bottom

Treating the levy as a line item that simply reduces final profit can miss the wider financing consequences.

The revised appraisal should establish where the liability sits in the development cash flow and what that does to peak funding.

A Pre-October Development Finance Review Should Recalculate:

  • Levy liability: using the applicable local-authority rate, chargeable floorspace and correct land classification.
  • Total development cost: incorporating the levy alongside construction, professional, planning and statutory costs.
  • Peak debt: identifying when the additional cash requirement occurs relative to facility utilisation.
  • Loan-to-cost: testing whether the revised scheme remains within the senior lender's parameters.
  • Loan-to-GDV: checking the overall debt position against the lender's valuation and projected end value.
  • Interest: allowing for any additional borrowing and changes to the development programme.
  • Contingency: ensuring the scheme still retains a realistic buffer for other cost movements.
  • Developer equity: identifying whether additional cash needs to be injected and at what stage.
  • Developer profit: calculating the revised profit on cost and profit on GDV after the levy.
  • Junior capital: testing whether mezzanine or stretch-senior funding remains viable at the revised margin.

A Scheme Can Remain Profitable but Become Harder to Finance

This is one of the most important distinctions for developers.

A scheme does not have to become technically loss-making before its finance becomes problematic.

Development lenders normally expect an appropriate level of developer equity and profit cushion. These protect the lender and sponsor against construction overruns, sales-value movements and delays.

If an additional statutory cost compresses that margin, the scheme may remain profitable in absolute terms while moving outside a lender's preferred credit parameters.

The developer can then face several possible outcomes: additional equity may be required, the senior facility may need to be restructured, junior funding may become more expensive, or the scheme itself may need to be redesigned.

That is why the Building Safety Levy should be considered as part of the capital stack rather than treated solely as a regulatory cost.

Timing Matters Because the Levy Is Connected to Building Control

Government guidance makes the commencement position particularly important. The levy applies to relevant applications for building control approval and notices submitted on or after 1 October 2026, subject to the detailed rules and exemptions.

Applications submitted before the commencement date are generally outside the levy regime even where relevant amendments are subsequently made, although a rejected application that has to be resubmitted on or after 1 October can become liable.

Developers should therefore establish the position for their actual building control route rather than assuming that planning permission, land acquisition or physical commencement alone determines liability.

The payment mechanics also have practical financing consequences. The levy must be paid before completion of the relevant building work or occupation, whichever occurs earlier, and the completion process can be affected where the liability remains outstanding.

For development finance, this means the cost needs to be incorporated into cash-flow planning rather than regarded as something that can simply be dealt with after the development has completed.

Existing Development Facilities Need to Be Checked

The first question for a developer with an existing facility should be whether the agreed funding already provides enough headroom to absorb the revised cost.

That requires more than looking at the headline facility limit.

A £10 million development facility does not necessarily mean the borrower can simply draw another £200,000 because a new cost has arisen. Drawdowns remain subject to the lender's agreed cost schedule, leverage tests, monitoring and facility terms.

If the original lender sized the loan against a specific cost plan, an increase in total development cost may require formal approval and potentially further sponsor equity.

Developers should therefore understand the impact before the additional cash is actually required.

The Question for Existing Borrowers

Does the current facility still fund the development on the revised cost plan — or will the sponsor discover near peak utilisation that additional equity is required?

What If the Existing Lender Will Not Increase the Facility?

Not every revised appraisal will create a problem. Some schemes will have sufficient contingency, equity and profit to absorb the levy without changing the financing.

Where the effect is more material, the appropriate solution depends on the stage of the development and the strength of the revised appraisal.

An existing lender may be prepared to increase the facility if the revised leverage remains acceptable and the borrower has performed well. In other cases, additional sponsor equity may be the simplest and cheapest solution.

Where the funding gap is larger, alternative senior development finance, stretch-senior lending, mezzanine debt or preferred equity may potentially be considered.

None of these structures should be used merely to preserve an appraisal that no longer makes commercial sense. Junior capital is more expensive than senior debt and can itself compress the developer's return.

The correct question is whether the revised project economics support the additional capital at a sensible risk-adjusted cost.

Land Acquisitions Need the Levy in the Residual Appraisal

The issue extends beyond schemes already under construction.

Developers considering new land acquisitions should ensure the levy is incorporated into the residual appraisal before agreeing the land price.

A residual land valuation effectively works backwards from the expected value of the completed development, deducting construction and associated costs, finance and the developer's required return to establish what can economically be paid for the land.

If a new statutory cost is omitted from that calculation, the residual land value can be overstated.

Once the site has been acquired, that error becomes much harder to correct. The landowner has already received the agreed price, leaving the additional cost to be absorbed elsewhere in the development economics.

The government's own impact assessment recognises this relationship between additional costs, land value and development viability.

Why Accountants, QSs and Project Monitors Should Be Reviewing This Now

The Building Safety Levy is particularly relevant to the professional advisers around a development because each sees a different part of the problem.

A quantity surveyor may identify the revised cost and chargeable floorspace. A development accountant may see the impact on cash flow, tax and profitability. A project monitor may see that the revised cost-to-complete position no longer fits comfortably within the available facility.

The finance adviser then needs to establish whether the existing capital stack remains appropriate.

Waiting until the borrower is short of cash materially weakens the available options. A developer approaching lenders with a fully revised appraisal and adequate remaining contingency presents a very different credit proposition from one seeking emergency capital because the existing facility has run out.

What Developers Should Do Before 1 October

Developers should first establish whether each relevant scheme falls within the levy regime and calculate the liability using the correct regulatory treatment.

That figure should then be incorporated into the development cash flow rather than considered separately.

The revised appraisal can be compared with the existing loan agreement, quantity surveyor's cost plan and latest lender monitoring report to establish whether there is sufficient facility headroom.

Where the revised position creates a potential funding gap, the developer can then discuss the position with the existing lender or explore alternative funding while there is still time to structure the solution properly.

The objective is not to refinance every affected development. It is to identify the minority where the new cost materially changes the capital requirement before it becomes an urgent problem.

How Willow Private Finance Can Help

Willow Private Finance works with property developers, housebuilders and professional advisers to structure development funding across senior, stretch-senior, bridging and junior-capital markets.

Where a development appraisal has changed, we can review the revised cost plan against the existing funding structure and establish whether the current facility remains appropriate.

That can include testing revised LTC and LTGDV, peak debt, additional equity requirements, facility headroom and the cost of alternative funding structures.

For developers approaching a new site acquisition, the finance can also be modelled against an appraisal that already incorporates the applicable levy rather than discovering the additional cost after land has been acquired.

Willow does not determine a developer's Building Safety Levy liability or provide legal, tax, building-control or quantity-surveying advice. The appropriate liability should be established with the relevant professional advisers and building control authority. Our role is to assess what the resulting numbers mean for the development finance.

Has the Building Safety Levy Changed Your Development Funding Requirement?

If a revised cost plan has increased peak debt, reduced developer margin or created an additional equity requirement, Willow can assess whether the existing facility still works and compare alternative senior, stretch-senior, bridging and development funding structures.

Explore Development Finance

Frequently Asked Questions

The Building Safety Levy introduces a new cost into qualifying residential development, with potentially important implications for development appraisals and funding.

When does the Building Safety Levy start?

The Building Safety Levy comes into operation in England on 1 October 2026. Subject to the relevant charging conditions and exemptions, it applies to qualifying building control applications or notices submitted on or after that date. Applications submitted before 1 October are generally outside the regime, although developers should check the detailed rules for their particular building control position.

How is the Building Safety Levy calculated?

The levy is principally calculated using chargeable residential floorspace and an applicable rate per square metre set for each local authority. Rates therefore vary by location. Developments meeting the regulatory definition of a previously developed site receive a levy rate equal to half the standard rate for that local authority.

Can the Building Safety Levy affect development finance?

Yes. Where the levy increases total development cost, it can alter peak debt, loan-to-cost, developer equity requirements, contingency and profit. If the existing senior facility is already close to its agreed leverage limits, the borrower may need to contribute additional equity or consider a different funding structure.

Does the Building Safety Levy apply to every residential development?

No. The legislation contains charging conditions and exemptions, including treatment for certain types of accommodation and development. The precise liability should be established against the regulations and government guidance rather than assumed simply because a scheme contains residential property.

Should an existing development appraisal be updated before October 2026?

If a scheme may fall within the levy, it is sensible to incorporate the actual expected liability into the appraisal and development cash flow. Developers can then reassess total cost, LTC, LTGDV, peak debt, equity, contingency and profit and establish whether the existing finance remains sufficient before the additional capital is required.

Development Finance Review

Does Your Development Facility Still Work on the Revised Numbers?

A relatively small change in total development cost can create a much larger funding problem when a scheme is already close to its leverage limits.

If the Building Safety Levy has changed your development appraisal, Willow Private Finance can assess the revised funding requirement against your existing senior facility and the wider development-finance market.

We can compare senior development debt, stretch-senior structures, bridging and junior capital where appropriate, while testing the effect on LTC, LTGDV, peak debt, sponsor equity and overall finance cost.

The earlier a potential funding gap is identified, the more opportunity there is to structure the capital properly rather than attempting to solve it when the existing facility is already close to full utilisation.

The question before 1 October is simple: does the facility and equity structure still work once the Building Safety Levy is included?

Important Notice

This article is provided for general information only and does not constitute personalised mortgage, development-finance, investment, legal, tax, accounting, planning, building-control or quantity-surveying advice.

The Building Safety Levy comes into operation on 1 October 2026 under the applicable legislation. Whether a particular development is chargeable, the floorspace included in the calculation, whether an exemption applies and whether a site qualifies for the previously developed land rate depend on the regulations and the facts of the individual scheme.

Developers should obtain appropriate advice from their building-control, legal, tax, accounting and other professional advisers and refer to current government guidance when calculating any liability. Willow Private Finance does not calculate or certify Building Safety Levy liabilities.

Development finance is subject to lender underwriting, valuation, quantity surveyor or project-monitor assessment, borrower experience, planning and building-control status, construction costs, GDV, LTC, LTGDV, equity, development programme, exit strategy and other lender-specific requirements.

The availability of additional senior debt, stretch-senior funding, mezzanine finance, preferred equity or bridging should not be assumed simply because development costs have increased. Additional capital can materially affect the developer's return and should be assessed against the economics and risks of the individual project.

Development lending may be unregulated. Security may be taken over property, land and other assets, and failure to maintain payments or comply with facility terms can result in enforcement and loss of the secured assets.

Full Sources

Home Builders Federation — SME Developer Research

Home Builders Federation research examines the operating environment facing SME housebuilders, including development viability, the cumulative impact of regulation and the industry's concerns regarding the Building Safety Levy. The latest HBF and Quantum Development Finance sentiment findings reported in August 2026 provide the survey evidence referenced in this article.

https://www.hbf.co.uk/research-insight/

MHCLG — Building Safety Levy Guidance: Introduction

Official government guidance confirming that the Building Safety Levy comes into operation on 1 October 2026 and explaining the broad scope, implementation and building-control framework through which the levy will operate.

https://www.gov.uk/guidance/building-safety-levy-guidance/section-1-introduction

MHCLG — Building Safety Levy Guidance: Rates and Calculations

Official guidance explaining the levy calculation, local-authority rates, chargeable floorspace and the treatment of previously developed sites, including the 50% discounted rate where the regulatory requirements are met.

https://www.gov.uk/guidance/building-safety-levy-guidance/section-2-levy-rates-and-calculations

MHCLG — Building Safety Levy Guidance for Developers

Government guidance for residential developers covering levy information, evidence, previously developed land classification and the practical requirements applying through the building-control process.

https://www.gov.uk/guidance/building-safety-levy-guidance/section-3-advice-for-developers-of-residential-buildings

UK Legislation — Building Safety Levy (England) Regulations 2025

The statutory framework establishing the Building Safety Levy in England, including the applicable area rates and regulatory provisions governing the levy.

https://www.legislation.gov.uk/uksi/2025/1236/contents/made

Willow Private Finance — Development Finance

Willow's Development Finance Hub provides further information on property development funding, lender structures and financing for residential and commercial development projects.

https://www.willowprivatefinance.co.uk/development-finance