One flat buyer was 24 weeks into a purchase when they discovered the lease lacked statutory protection against certain building safety costs. The block had an A1 external wall rating. In evidence published by Parliament on 18 November, the buyer described the time and money already spent before they learned who might have to pay for future work.
The government wants to close a gap in England’s rules that can leave someone buying their only home exposed to repair bills because of who owned the flat in February 2022. The Building Safety (Remediation of Unsafe Cladding etc) Bill is at Commons committee stage, with the next sitting scheduled for 24 November. For buyers and owners trying to remortgage this week, the existing protections and the lender’s assessment of the building still determine whether an application can proceed.
Why a previous owner’s circumstances can hold up a sale
When a flat changes hands, the buyer can inherit the lease’s status under the Building Safety Act 2022. For a qualifying lease in a relevant building in England, the Act protects the leaseholder from charges for qualifying cladding remediation and can limit what they pay for certain other historical defects. The distinction matters when the work involves both the outer wall and fire precautions inside the block.
One eligibility test looks back to 14 February 2022. Subject to the other statutory conditions, the lease can qualify if the flat was the owner’s only or main home on that date, or if the owner held no more than three UK residential properties in total. A buyer who plans to live there today may therefore need evidence about someone they have never met.
The 24-week case came from the Non Qualifying Leaseholders Campaign Group. In another account submitted to MPs, a first-time buyer withdrew shortly before exchange after discovering the lease was non-qualifying. These are individual reports, but they explain why a buyer’s solicitor may ask for a leaseholder deed of certificate and the landlord’s certificate early in a purchase. The paperwork can establish which costs the buyer might inherit before they spend more on the transaction.
Who could gain protection under the proposals?
Ministers are exploring how to protect more people who buy a flat as their only home where the previous owner’s circumstances excluded the lease. For a seller, that could widen the pool of buyers able to proceed. For the buyer, it could remove a potential bill that is difficult to price into an offer. The government has yet to settle the detailed eligibility rules.
A second proposal would raise the multiple-property threshold from three to six. The government has linked this change to owners of four to six properties on the February 2022 date who missed out on protection from certain non-cladding costs. A landlord with four flats should establish which leases qualified under the original rules and what defects each building has. Counting the properties they own today gives only part of the answer.
There is a separate funding proposal for blocks where residents collectively own the building or have bought the freehold together. Ministers intend to help meet the cost of certain high-risk, high-cost fire defects inside these buildings. Anyone negotiating a purchase in such a block would still need to know which work qualifies, how much funding is confirmed and whether the residents face a balance.
These building safety proposals were announced on 27 October. The separate Commonhold and Leasehold Reform Bill introduced on 19 November deals with matters including ground rent and planning for major repairs. For a flat already on the market, the immediate financing question is who will pay for the defect identified in that building.
When a lender can consider a flat before repairs finish
A block awaiting work can still be considered for a mortgage. Nationwide’s published criteria for England illustrate how much turns on the stage reached. Where the Cladding Safety Scheme is involved, the lender asks for confirmation that the building has been found eligible. An acknowledgement that the owner has applied falls short. Nationwide also asks for a summary of planned works and information about interim measures.
If a developer is paying, Nationwide asks for a dated, signed letter identifying the work it will cover and any costs left to individual leaseholders. It also asks the responsible party for information about interim fire precautions. A developer’s name on a national list is of limited use to the buyer if it is unclear whether the commitment covers their particular block or every defect in the report.
That distinction gives someone approaching the end of a fixed rate a practical starting point. Ask the managing agent for the latest funding decision, the works schedule if available, and any charges passed to the flat. An adviser can then check what a new lender would require for a remortgage and what the existing lender can offer for a rate switch. The two enquiries can run alongside each other while a missing document is obtained.
What an EWS1 form tells a mortgage valuer
The Royal Institution of Chartered Surveyors updated its cladding valuation standard with effect from 1 November. It sets out when a valuer should seek an EWS1 form, which summarises an assessment of the external wall for lending purposes. A valuer can take an established route to remediation into account, subject to the lender’s instructions. An EWS1 is neither compulsory for every flat sale nor a certificate covering the safety of the whole building.
That explains how a buyer could see an A1 rating yet still have legitimate questions for their solicitor. The external wall assessment concerns the building. The lease and certificates establish which statutory protections pass to the buyer. If the seller provides only one half of that evidence, the other question remains open.
Royal Gateway raises a different question about the structure
In October, residents at Royal Gateway in Canning Town were told to leave after concerns emerged about cracking in transfer slabs. Newham Council identified Centurion Tower, Sovereign Tower and St Vincent’s Court in its dangerous-structures notice. A transfer slab carries the weight of columns or walls above it to supports in different positions below, a feature sometimes used where flats sit above an open-plan commercial floor.
The Building Safety Regulator advises building owners to seek professional advice where there are signs of distress or specific concerns about the design. The presence of a transfer slab alone does not establish that a building is unsafe. Where a particular block is under investigation, the documents relevant to a purchaser are the structural engineer’s findings, any restrictions on occupation and the proposed work. A cladding funding letter answers none of those questions.
Willow’s earlier reporting examined how the years left on a lease can narrow mortgage choice. A flat can have a long lease and still present a lending difficulty if responsibility for repairs is unresolved. Before exchange, the buyer’s solicitor can confirm the liability attaching to the lease, the managing agent can supply the building records, and the mortgage adviser can put both to the proposed lender. Read Willow’s report on short leases and mortgage eligibility.
Buying or remortgaging a flat awaiting building safety work?
Willow can check the evidence a lender needs for your block, including a developer’s funding letter, the status of planned works and any costs identified by your conveyancer.
Explore residential mortgage optionsFrequently Asked Questions
Questions buyers and owners ask about cladding, repair bills and mortgage evidence.
Can I get a mortgage on a flat before cladding repairs start?
Some lenders will consider it. Evidence might include confirmation that the block is eligible for a remediation scheme or a signed developer commitment. The lender will assess the valuation, any costs left to the leaseholder and its own criteria.
Why does 14 February 2022 matter if I buy a flat now?
Under the current rules in England, the lease’s protected status can depend on the owner’s circumstances on that date. That status can pass with the lease. Your conveyancer can check the relevant certificates and explain your exposure before exchange.
Does the proposed six-property limit apply now?
No. The current property-count threshold is generally three UK residential properties, with a separate route where the flat was the owner’s only or main home. Ministers propose extending the threshold to six for certain non-cladding costs.
Do I need an EWS1 form for every leasehold flat?
No. The lender and valuer consider the building, available assessments and any funded repairs. An EWS1 records external wall information for valuation purposes. A separate structural concern may require an engineer’s report.
What should I request before trying to remortgage an affected flat?
Ask the managing agent for the current assessment, written funding decision, works timetable if available and details of charges to your flat. Gather any relevant leaseholder and landlord certificates so your adviser can check the lender’s evidence requirements.